It reads (per »www.illinois1call.com/law_enforc···_2.9._):

"Provide notice not less than 48 hours but no more than 14 calendar days in advance of the start of the excavation or demolition to the owners or operators of the underground utility facilities or CATS facilities in and near the excavation or demolition area through the State‑Wide One‑Call Notice System"

Which means that the excvator must give at least 2 day notice and work must begin within 14 days. Which means you can't call today and do the work in 3 months.

So again, it's basically two working days.